This litigation arose between a general contractor and the electrical subcontractor after they built a service station and restaurant in Ripon. By special verdict, the jury found the general contractor liable to the electrical subcontractor under both contract and rescission theories. On appeal, the general contractor asserts, mainly, that the evidence does not support the contract remedies. It does not likewise assert the restitutionary relief available under the rescission theory was flawed. Court conclude the general contractor has failed to show prejudicial error and, therefore, affirm.