IN THE COURT OF APPEAL OF THE STATE OF CALIFORNIA
SECOND APPELLATE DISTRICT
DIVISION THREE
PACIFIC COLLECTIVE, LLC, B339582
Plaintiff and Appellant, (Los Angeles County
Super. Ct. No. 22SMCV02016)
v.
ORDER MODIFYING OPINION
TGS CC VENTURES, LLC, et al., [NO CHANGE IN JUDGMENT]
Defendants and Respondents.
THE COURT:
It is ordered that the opinion filed herein on October 12,
2026, be modified to reflect that the Los Angeles County Superior
Court case number is 22SMCV02016.
____________________________________________________________
ASHWORTH, J.* ADAMS, P. J. HANASONO, J.
* Retired Judge of the El Dorado County Superior Court,
assigned by the Chief Justice pursuant to article VI, section 6 of
the California Constitution.
Filed 10/12/26 Pacific Collective v. TGS CC Ventures CA2/3 (unmodified opinion)
NOT TO BE PUBLISHED IN THE OFFICIAL REPORTS
California Rules of Court, rule 8.1115(a), prohibits courts and parties from citing or relying on
opinions not certified for publication or ordered published, except as specified by rule
8.1115(b). This opinion has not been certified for publication or ordered published for
purposes of rule 8.1115.
IN THE COURT OF APPEAL OF THE STATE OF CALIFORNIA
SECOND APPELLATE DISTRICT
DIVISION THREE
PACIFIC COLLECTIVE, LLC, B339582
Plaintiff and Appellant, (Los Angeles County
Super. Ct. No. 22SMCV052016)
v.
TGS CC VENTURES, LLC, et al.,
Defendants and Respondents.
APPEAL from a judgment of the Superior Court of
Los Angeles County, H. Jay Ford III, Judge; Gerald Rosenberg
(Ret.), Referee. Affirmed.
Kowal Law Group, Timothy M. Kowal, Teddy T. Davis and
Richard J. Radcliffe for Plaintiff and Appellant.
Pettit Stein, Eric S. Pettit; King & Spalding and Craig H.
Bessenger for Defendants and Respondents.
Appellant Pacific Collective, LLC (Pacific) is a real estate
developer. In 2018, Pacific entered into a lease with defendant
TGS CC Ventures, LLC (TGS) which provided that Pacific would
purchase real property in Culver City (the City) and build a
cannabis dispensary on it. TGS would apply for a cannabis
license and rent the property for 15 years. TGS’s parent,
defendant Jushi, Inc. (Jushi), guaranteed TGS’s lease obligations.
TGS rescinded the lease in February 2020. By that time, it
had applied for a cannabis permit and had been chosen by the
City to move forward with the permitting process. However,
Pacific still had not purchased the property, despite TGS’s and
Jushi’s repeated requests to do so. Instead, Pacific repeatedly
delayed entering into a purchase agreement and then sought to
extend its closing date.
Pacific sued TGS and Jushi for breach of contract,
contending that defendants rescinded the lease without legal
cause. The case was tried to a referee, who found that
defendants were within their rights to rescind the lease because
Pacific breached its obligation to purchase the property within a
reasonable time. We find no error, and thus we affirm.
FACTUAL AND PROCEDURAL BACKGROUND
I. The dispute.
A. The option agreement and the lease.
Pacific is a limited liability company that develops real
estate. At all relevant times, Pacific’s members were Rahul
Paliwal and David Yanko.1
1 Yanko withdrew from Pacific in 2022 but retains an
economic interest in this litigation.
2
Jushi is a national cannabis company that develops and
operates retail cannabis dispensaries. TGS is a Jushi subsidiary.
In spring 2018, Paliwal and Yanko learned that
ExxonMobil Oil Corporation (ExxonMobil) was selling a piece of
real property located at 3800 Sepulveda Boulevard, Culver City
(the property). The property was in the City’s “green zone”—the
area where the City allowed retail cannabis dispensaries.
Paliwal met Jushi’s Chief Strategy Director, Trent
Woloveck, through a broker. Between April and September 2018,
Paliwal and Woloveck discussed structuring a deal in which
Pacific would purchase the property and lease it to TGS to
operate a cannabis dispensary.
On September 24, 2018, Pacific and ExxonMobil entered
into an option agreement. The option agreement provided that
ExxonMobil would remove the property from market until
November 15, 2018 (the option period) “to allow for the
negotiation and execution of a Sale and Purchase Agreement
between Pacific Collective and ExxonMobil.” In exchange, within
three days of the agreement’s effective date (that is, by
September 27, 2018), Pacific would pay ExxonMobil a
nonrefundable deposit of $50,000. During the option period, the
parties would “negotiate in good faith” a purchase agreement
that would include agreed-upon terms, including a purchase price
of $4.2 million, a six-month due diligence period that could be
extended by up to four months, and a closing date no later than
10 days after the expiration of the due diligence period. If the
parties failed to execute a purchase agreement by November 15,
2018, the option agreement would “expire and neither party will
have any rights or obligations hereunder” unless the parties
agreed in writing to extend the option period.
3
Meanwhile, Pacific and TGS entered into a lease on
September 26, 2018, and Jushi signed a lease guarantee the next
day. The lease provided that Pacific would construct a 5,000
square foot building on the property that it would rent to TGS for
15 years. Construction costs would not exceed $1.75 million, and
rent would be $20 per square foot for the first year and would
increase over time.
The lease contained the following terms that are relevant to
the present dispute:
Purchase contingency (§ 1.21): “[T]he parties agree that
this Lease is contingent upon the transfer of fee title to the Land
to [Pacific] pursuant to [the purchase agreement] by and between
[ExxonMobil], as Seller, and [Pacific], as Buyer. [Pacific]
represents and warrants it has a valid and enforceable right to
purchase the Land. [Pacific] hereby represents that upon
completion of the transactions contemplated by the Purchase
Agreement, it will own the Land in accordance with the title
policy obtained by [Pacific] pursuant to the Purchase Agreement.”
Possession (§ 4.2): “[Pacific] shall deliver possession of the
Premises to [TGS] upon completion of construction of the
Building Improvements . . . .”
Time (§ 31.7): “Time is of the essence with respect to
performance of every provision of this Lease in which time or
performance is a factor.”
Cannabis license contingency (§ 1.18): TGS “shall, at [its]
sole cost and expense, apply for a [cannabis license] . . . with the
City . . . promptly following the Effective Date and . . . shall
diligently pursue the [cannabis license]. If [TGS] fails to obtain
its [cannabis license] within eight (8) months following the
Effective Date of this Lease (the ‘License Contingency Period’),
4
then [TGS] shall have the right to terminate this Lease upon
delivery of written notice to [Pacific] . . . on or before fifteen (15)
days following the expiration of the License Contingency Period.”
If TGS exercised its right to terminate the lease under this
provision, it would be required to pay “termination consideration”
of $75,000.
Entitlement and development contingency (§ 1.19):
“[Pacific] and [TGS] shall cooperate in good faith to expeditiously
obtain all requisite entitlement, use[,] and development permits
and approvals for the Building (including a building permit)
(collectively, the ‘Approvals’). If the City . . . does not issue the
Approvals . . . within thirty-six (36) months following the
Effective Date (the ‘Entitlement Contingency Period’), then either
[Pacific] or [TGS] shall have the right to terminate this
Lease . . . .” In the event of termination, TGS agreed to pay
Pacific “all soft costs and losses which [Pacific] may reasonably
suffer . . . not to exceed a maximum termination fee payable by
[TGS] of $250,000, which amount the parties agree will be
liquidated damages.”
Improvements (§ 1.15): Pacific “shall not be obligated to
construct the improvements until [TGS] has submitted to
[Pacific] all applicable state and local licenses, permits and
approvals to operate a storefront retail cannabis business from
the Premises.”
On September 28, 2018, Pacific wired ExxonMobil a
nonrefundable deposit of $50,000.
B. TGS’s application for a cannabis business
license.
On September 27, 2018, TGS submitted a cannabis license
application. The application required TGS to identify the
5
property’s owner, who had to sign a consent form. While TGS
was preparing its application, Jushi’s attorney, Matt Leeth,
asked Paliwal to confirm that Pacific owned the property,
explaining that its lease “must be with the property owner or else
we need to otherwise document the connection.” Paliwal
responded that Pacific “is the contract purchaser for the property
and it is my Attorney’s understanding along with our Public
Affairs consultant that the contract purchaser can sign the
Property Consent Form.” Leeth asked for a copy of the option
agreement, and Paliwal sent Leeth a redacted copy on September
26, 2018.
C. Extensions of Pacific’s option to purchase the
property (November 2018 to November 2019).
ExxonMobil provided Paliwal with a draft purchase
agreement for the property on October 25, 2018, less than a
month after the parties entered into the option agreement.
Paliwal did not respond until November 21, 2018, after the option
period had expired.
Sometime in November 2018, Pacific obtained an extension
of the option period to March 1, 2019. Pacific did not execute a
purchase agreement by March 1, 2019, and it did not tell TGS
that its option period had expired.
In April 2019, Paliwal spoke to ExxonMobil’s attorney,
Brian Steelman at ExxonMobil about getting the property “back
under contract.” As part of those discussions, Paliwal asked for a
further extension of the option period to allow TGS to “get[ ] . . .
through the licensing period.” Ultimately, Pacific obtained a
further extension of the option period to May 31, 2019. Pacific
did not execute a purchase agreement with ExxonMobil by that
date.
6
On May 30, 2019, Steelman emailed Paliwal that “the
Option Agreement will expire tomorrow” and asked Paliwal to
“reach out . . . to discuss next steps.” Paliwal and Steelman
exchanged emails in June and July, but the parties did not
extend the option agreement or execute a purchase agreement at
that time.
On July 24, 2019, the City notified TGS that it had been
selected as one of three applicants to move forward with the
cannabis license application process. The next steps were for
TGS to participate in a community meeting, and then to submit a
Preliminary Project Review request (PPR request).
In September 2019, Jushi circulated a draft PPR request to
Paliwal and Yanko and asked them whether any changes were
needed. Although the attached draft identified Pacific as the
“property owner,” Paliwal did not tell TGS or Jushi that Pacific
still did not own the property, had not entered into an agreement
to purchase the property, and no longer had an enforceable option
to purchase the property.
Sometime between August and October 2019, Woloveck
spoke to Paliwal and asked him to close on the purchase of the
property. Woloveck said neither Paliwal nor anyone else ever
provided him with copies of any of the extensions of the option
agreement.
On October 17, 2019, TGS participated in a community
meeting to allow city residents to express concerns or objections
to the cannabis license applicants. Woloveck testified that
nothing at that meeting suggested that TGS would not obtain a
cannabis license.
7
D. Pacific’s execution of the purchase agreement
with ExxonMobil.
On November 5, 2019, Pacific signed an agreement to
purchase the property for $4.2 million. The sale would close “no
later than December 16, 2019.” Pacific was required to deposit
earnest money of $70,000 within three days of the agreement’s
effective date. Time was “of the essence” and “strict compliance”
was required “as to all dates and time periods set out herein.”
Although Paliwal signed the purchase agreement on
November 5, 2019, he did not immediately deposit the earnest
money or prepare to close on the property. He also did not share
the purchase agreement with TGS or Jushi. Instead, on
December 11, 2019, Paliwal sent a letter to ExxonMobil to update
it on Pacific’s “timeline for closing on the property.” Paliwal said
Pacific “anticipat[ed] needing until April 15, 2020 to complete the
business license process for our tenant in order to close on the
property.” Paliwal attributed the delay to the City’s delays in
issuing TGS a cannabis license. At trial, however, Paliwal
conceded that TGS’s completion of the licensing process was not
necessary for Pacific to purchase the property. Paliwal also
conceded that he did not tell anyone at TGS or Jushi that he did
not intend to close until after TGS obtained a cannabis license,
and there was no evidence at trial that Paliwal told TGS or Jushi
that he hoped to extend the closing date to April 15.
8
E. Conflicts develop between Pacific and TGS.
The City advised TGS that the earliest it could submit the
PPR request was one week after the community meeting, or on
October 24, 2019. TGS had prepared a draft submission by that
date, but it had begun to question whether Pacific would close on
the property. It therefore was unwilling to submit a PPR request
identifying Pacific as the property’s owner.
On November 18, 2019, Jushi’s CEO, James Cacioppo,
asked Olivier Blechner, Jushi’s head of business development, to
contact Paliwal to discuss the status of the project because “[w]e
were concerned that the property wasn’t purchased yet.”
Blechner and Paliwal spoke the same day. Blechner was
surprised that Pacific didn’t yet own the property and “took the
view that [Pacific] didn’t have the money today and [had] very
little chance at getting money in the future, given what [Paliwal
said] about the process.”
On November 26, 2019, Cacioppo met with Paliwal and
Yanko. According to Paliwal, Cacioppo demanded a 50 percent
reduction in the size of the building and a 50 percent rent
reduction, and he said he would “gladly walk away from the deal”
if Paliwal and Yanko did not agree to those revised terms.
Woloveck, Blechner, Paliwal, and Yanko spoke by phone on
December 11 or 12, 2019. The call was “pretty testy.” According
to Woloveck, Paliwal and Yanko said they were working on
financing but did not yet have anything in place. Paliwal and
Yanko nonetheless urged Blechner and Woloveck to submit the
PPR request immediately, contending that TGS could represent
that Pacific was the property owner even though the sale had not
closed. Blechner and Woloveck refused, “since it isn’t true.” The
parties also discussed reducing TGS’s rent, and Blechner
9
suggested stepping into Pacific’s shoes and taking over the
project.
During a follow-up conversation with Yanko sometime in
mid to late December, Woloveck said he was not willing to submit
a PPR request identifying Pacific as the property’s owner until
Pacific closed.
On December 23, 2019, Yanko wrote to Woloveck that it
would not grant Jushi’s request for a reduction in rent. Instead,
Yanko said he would consider reducing the rent to $1 in exchange
for TGS’s agreement to pay all construction costs and make a
cash payment to Pacific of $8 million. TGS did not respond to
that offer.
On January 2, 2020, TGS’s attorney sent a letter to Pacific
threatening to rescind the lease. In material part, the letter said
that the lease was illusory and unenforceable because it did not
provide a time within which Pacific had to acquire title to the
property. The letter said TGS nonetheless was not rescinding at
that time and remained “willing to discuss a resolution that may
serve to salvage the purported Lease.”
On January 9, 2020, Pacific responded that the purchase
contingency was not illusory, and TGS’s threat to refuse to abide
by the terms of the lease was “an improper attempt to
renegotiate” the lease. Pacific nonetheless agreed to participate
in settlement negotiations with TGS. The appellate record does
not indicate whether those settlement negotiations happened.
As of February 7, 2020, Pacific still had not deposited the
$70,000 earnest money payment with ExxonMobil. That day,
Steelman emailed Paliwal that the purchase agreement
“specifically lays out the timing of [the earnest money] payment;
both parties signed that agreement in late 2019 with the full
10
understanding and expectation that we would close in 2019. . . .
We are now almost 90 days into a mutually agreed upon
[purchase agreement] with no financial commitment from
[Pacific]—which is unacceptable.” Steelman said ExxonMobil
was willing to work with Pacific on a new closing date, but would
not do so unless Pacific made the $70,000 earnest money
payment. Steelman noted that “both parties had previously
agreed to close in December of 2019 and that time was of the
essence.”
On February 7, 2020, Pacific and ExxonMobil signed an
amendment to the purchase agreement that required Pacific to
deposit the earnest money by the end of the day and extended the
closing date to March 31, 2020. Pacific made the $70,000 earnest
money payment the same day.
F. TGS’s rescission of the lease.
On February 28, 2020, TGS formally rescinded the lease
“based on mistake, fraud, and failure of consideration” because
Pacific had “faile[ed] to perform its obligations under the
Commercial Lease within a reasonable time.” TGS asserted it
had “not received anything of value from the Commercial Lease
and thus has nothing to restore to [Pacific] pursuant to California
Civil Code section 1691(b).”
After Paliwal received the rescission letter, he entered into
a letter of understanding with another cannabis retailer,
MedMen. However, Pacific did not move forward with MedMen.
Paliwal contacted another real estate broker once it became clear
Pacific could not bring in another marijuana user on this site, but
he was not able to find a tenant willing to offer anything close to
the deal Pacific had with TGS. Ultimately, Pacific did not
purchase the property.
11
In December 2020, TGS bought the property from
ExxonMobil.
II. The present litigation.
In October 2022, Pacific filed a complaint alleging breach of
the lease by TGS and breach of the guaranty by Jushi. The first
cause of action alleged that TGS breached the lease by
“terminating the Lease without the right to do so,” and the
second cause of action alleged that Jushi “fail[ed] to satisfy its
obligations under the Lease Guaranty by allowing the Lease to be
terminated without the right to do so.” Pacific alleged its
damages exceeded $20 million.
In April 2023, the trial court appointed retired Judge
Gerald Rosenberg to act as a referee pursuant to the lease’s
dispute resolution provision. The case was tried before
Judge Rosenberg over five days in January 2024.
A. Pacific’s case.
In total, Pacific needed to raise $4.2 million to buy the
property, plus an additional $1.75 million in construction costs.
Paliwal testified that when he signed the lease agreement with
TGS in September 2018, he didn’t yet have the capital necessary
to purchase the property and hadn’t started sourcing it. He also
did not have capital in place or offering documents finalized when
he signed the purchase agreement on November 5, 2019, when he
received the rescission letter on February 28, 2020, or by Pacific’s
last day to close, March 31, 2020. However, Paliwal had “no
doubt” that Pacific would have been able to purchase the property
by March 31, 2020 had TGS not rescinded because “[w]e had
commitments, capital commitments from investors, and we also
had a commitment from a potential lender.”
12
Paliwal testified that once he signed the purchase
agreement on November 5, 2019, he started drafting offering
documents and getting funding commitments in place. Paliwal
said he had “soft commits” at that time—convertible notes of
$425,000, and a “soft commit” of funds from his father,
Dr. Yogesh Paliwal (Yogesh). Paliwal also began contacting
equity providers and lenders prior to February 28, 2020. He
received letters of interest from two lenders: from iBorrow on
March 13, 2020, and from Balour on March 11, 2020.
Paliwal testified that Pacific didn’t purchase the property
prior to February 28, 2020 for “practical” reasons, because “the
minute we take in the money, the preferred return on that money
starts accruing right away. So we like to take in the capital right
when we’re going to be closing on the deal to save on expenses.”
Paliwal also testified that he did not complete the private
placement documents necessary to raise the funds for the
purchase prior to February 28 because Pacific was “subject to a
re-trade by TGS.” He explained that there was never a time after
the November 2019 dinner with Cacioppo that he felt comfortable
closing on the deal with ExxonMobil because “[w]e did not know
what the final deal would be or even [if] what TGS would be
demanding would be viable for us to accept.” Ultimately, Paliwal
said, Pacific did not finalize offering documents or fund the deal
because “there was no deal left. The lease that we had signed
with TGS was for a build-to-suit, and after they had rescinded
the lease, there was no tenant. And there’s no build-to-suit lease
left.” Paliwal said TGS’s rescission was the only reason Pacific
did not take the loans offered by iBorrow and Balour.
Paliwal conceded on cross-examination that the redacted
copy of the option agreement he provided to TGS before the
13
parties signed the lease contemplated that a purchase agreement
would be executed within two months, i.e., by November 2018.
He also conceded that although he asked ExxonMobil to extend
the closing date until after TGS obtained a cannabis license, he
never told TGS or Jushi that he did not intend to close on the
property until TGS obtained a cannabis license. And, Paliwal
agreed that nothing in the lease made Pacific’s obligation to
purchase the property contingent on anything, including on TGS
obtaining a cannabis license, or permitted Pacific to delay its
obligation to purchase the property. He agreed that TGS could
not get a cannabis license until it submitted its PPR request,
which required it to identify the property’s owner.
Paliwal’s father, Yogesh, testified that had the project
closed by March 31, 2020, he would have invested $500,000. Two
other potential investors, Aliyah Govani and Wallace Cheng,
testified that they had committed to investing $1.5 million each.
However, Govani said he would not have invested without seeing
offering documents, which Paliwal never provided. Cheng
testified that he would have invested in the project only if Pacific
had agreed to amend the LLC agreement and give Cheng a
ten percent bonus; Paliwal never told Cheng that Pacific would
agree to these terms.
B. Defendants’ case.
Woloveck testified that when TGS entered into the lease
with Pacific, TGS did not know that Pacific was going to try to
delay purchasing the property until after TGS obtained a
cannabis license from the City. By late February 2020, TGS was
ready to move forward on the property and the City was asking
for updates. TGS couldn’t move forward because Pacific hadn’t
closed on the property.
14
Woloveck testified that TGS could not submit the PPR
request at any point prior to February 2020 because TGS’s lease
was with Pacific, who still did not own the property. Further, the
City wouldn’t award TGS a cannabis license until the building
was complete.
Woloveck believed Pacific should have closed on the
property in July 2019, once TGS learned it had been selected to
move forward with the licensing process. Woloveck said he orally
asked Paliwal and Yanko many times to close on the purchase of
the property. Paliwal and Yanko always responded that they
were working on it, but they were never specific about their
efforts. In November and December 2019, Woloveck formed the
opinion that Pacific would not be able to close because they didn’t
have the necessary financing. He explained: “If they would have
had the money to close, they would have closed.”
Woloveck testified that he participated in the decision to
rescind, which he believed was warranted because Pacific had
failed within a reasonable time to perform its obligations to
purchase the property, build a building, and deliver possession of
a completed cannabis dispensary. He said TGS rescinded when it
did because it believed Pacific had had plenty of time and still
was not in a position to raise the money in the next 32 days. “So
we ripped the band-aid off and sent them the [rescission] letter.”
Woloveck further testified that the only reason TGS did not
submit the PPR request between November 2019 and February
2020 was because it did not feel comfortable identifying Pacific as
the owner of the property.
Blechner testified that TGS did not submit the PPR request
in December because Pacific “didn’t own the property” so TGS
“had no way of submitting the PPR [request] in a way that would
15
satisfy the criteria and conditions that the City imposed.” After
speaking with Paliwal in November 2019, Blechner believed that
Paliwal did not have the money to purchase the property and had
very little chance of getting it in the future. He explained that
the two firms Paliwal hoped to borrow from had lent significant
amounts of money to MedMen, another California-based cannabis
firm, who was in financial trouble. If those investors lost money
with MedMen, Blechner believed that raising money to finance a
cannabis venture would become even more difficult. Blechner
testified: “I’ve been involved in a lot of fundraising in my
professional life, and my summary would be they [were]
absolutely nowhere.”
Blechner testified that by February 2020, he had
“completely lost trust in anything” Paliwal told him. He
supported the decision to rescind the lease because Pacific
“[could] not perform, ha[d] shown no ability to perform, ha[d]n’t
raised money to perform.”
C. Statement of decision.
In March 2024, the referee issued a statement of decision
finding for TGS and Jushi and against Pacific. The referee made
the following findings:
Whether the purported rescission was effective depended,
in significant part, on whether Pacific fulfilled its obligations
under the lease. Section 4.2 of the lease required Pacific to
deliver possession of the property to TGS upon completion of
construction. In order for Pacific to deliver possession, it first
had to acquire title to the property from ExxonMobil. Instead, of
acquiring title, Pacific “was doing the following:
“a. Mr. Paliwal was stalling: On December 11 or 12,
2019, Trent Woloveck was in Las Vegas with Olivier Blechner at
16
a cannabis convention. On one of these dates, they participated
in a telephone call with Rahul Paliwal and David Yanko. During
the call, Mr. Paliwal stated that they were ‘working on financing
to buy [t]he Property.’
“b. Mr. Paliwal was seeking more time to close escrow:
On December 11, 2019, [Pacific] sent a letter to Brian F.
Steelman of ExxonMobil with a progress report regarding its
purchase of [t]he Property. In the letter, Mr. Paliwal stated, ‘we
are anticipating needing until April 15, 2020 to complete the
business license process for our tenant in order to close on the
property.’
“c. Mr. Paliwal was able to extend the closing date one
last time: On February 7, 2020, [Pacific] and ExxonMobil entered
into a First Amendment of Sale and Purchase Agreement. The
Amendment provided ‘the closing date to be no later than
March 31, 2020.’ ExxonMobil would not extend the closing
beyond March 31, 2020.
“d. Mr. Paliwal did not comply with one of the terms of
[the purchase agreement]; he failed to deposit $70,000.00 into
escrow within 3 days of November 5, 2019. . . .
“e. Mr. Paliwal had to raise $4,200,000.00 to close
escrow and $1,750,000.00 to develop [t]he Property for [TGS].
“f. Mr. Paliwal had limited cash resources . . . . The
balance sheet of [the entity created to hold title to the property]
. . . showed funds on deposit in the sum of $3,325.27 just before
the Notice of Rescission was issued.
“g. The convertible noteholders never converted the
loans into equity . . . .
“h. Mr. Paliwal explored loans from iBorrow, Bolour, and
Hanke Capital. He never obtained financing from any of them.
17
[¶] . . . No offering documents nor subscription agreements were
prepared in anticipation of raising capital.
“The evidence is clear, at no time prior to the notice of
rescission did Mr. Paliwal have the capital to purchase [t]he
Property nor was he able to borrow the necessary funds to close
the escrow and develop [t]he Property.
“At the [t]rial, Mr. Paliwal was asked, ‘Did you have any
doubt, Mr. Paliwal, that you would be able to close on the
purchase with Exxon?’ In response, Mr. Paliwal stated that he
had no doubt and stated, ‘We had commitments, capital
commitments from investors, and we also had a commitment
from a potential lender, too.’
“[Mr. Paliwal was asked]: ‘Offering documents, private
placement memorandum, subscription agreements. Is that
something you could complete by March 1, 2020? In response,
Mr. Paliwal stated, ‘No.’
“[Mr. Paliwal was then asked]: ‘Prior to February 28, 2020,
were you at that point, prior to the termination notice, to
complete a private placement memorandum?’ In response,
Mr. Paliwal stated, ‘we were not able to complete it because we
were subject to a re-trade by TGS . . . we did not know what the
final deal would be.’
“Mr. Yanko testified at the [t]rial that a Subscription
Agreement was needed in order to raise funds regarding [t]he
Property. At no time did Mr. Paliwal prepare and obtain signed
Subscription Agreements from investors. [¶] . . . [¶]
“Plaintiff never closed escrow regarding its purchase of
[t]he Property.
“Plaintiff never had the necessary funds or loan
commitments to purchase [t]he Property.
18
“The lease provided, ‘time is of the essence.’
“It was clear to Defendants that Plaintiff was not able to
purchase [t]he Property within a reasonable time after the
execution of the lease, and that Mr. Paliwal was stalling for time.
Plaintiff therefore breached its obligation under the lease and
Defendants were within their rights to rescind the lease and the
guaranty.”
The trial court entered judgment for defendants on May 28,
2024. Pacific timely appealed from the judgment.
DISCUSSION
I. Standard of review.
“A general reference occurs where the court, with the
consent of the parties, directs a referee to try any or all of the
issues in the action. . . . In the case of a general reference, the
referee must prepare a statement of decision which stands as the
decision of the court and is reviewable in the same manner as if
the court had rendered it.” (Sy First Family Ltd. Partnership v.
Cheung (1999) 70 Cal.App.4th 1334, 1341, citing Code Civ. Proc.,
§§ 638, 644.)
On appeal from a judgment following a bench trial, we
review the trial court’s conclusions of law de novo and its findings
of fact for substantial evidence. (McPherson v. EF Intercultural
Foundation, Inc. (2020) 47 Cal.App.5th 243, 257; Central Valley
General Hospital v. Smith (2008) 162 Cal.App.4th 501, 513.)
Under the substantial evidence standard of review, “ ‘ “[w]e
accept the trial court’s resolution of credibility and conflicting
substantial evidence, and its choice of reasonable inferences that
can be drawn from the evidence.” ’ ” (City of San Clemente v.
Department of Transportation (2023) 92 Cal.App.5th 1131, 1149.)
19
II. The referee did not err by entering judgment for
TGS and Jushi.
A. Overview.
Both of Pacific’s causes of action are for breach of contract.
A breach of contract “is ‘[t]he wrongful, i.e., the unjustified or
unexcused, failure to perform’ the terms of a contract.” (Chen v.
PayPal, Inc. (2021) 61 Cal.App.5th 559, 570.) The elements of a
cause of action for breach of contract are (1) the existence of the
contract, (2) plaintiff’s performance or excuse for
nonperformance, (3) defendant’s breach, and (4) plaintiff’s
resulting damages. (Oasis West Realty, LLC v. Goldman (2011)
51 Cal.4th 811, 821; Coyote Aviation Corp. v. City of Redlands
(2025) 111 Cal.App.5th 955, 973.)
Pacific’s theory at trial was that TGS and Jushi breached
the lease by rescinding in February 2020 without legal cause. A
party to a contract may rescind a contract “if there is a material
breach by the other party.” (Pennel v. Pond Union School Dist.
(1973) 29 Cal.App.3d 832, 838; see also Civ. Code, § 1689,
subd. (b)(2) [party to a contract may rescind “[i]f the
consideration for the obligation of the rescinding party fails, in
whole or in part, through the fault of the party as to whom he
rescinds”]; Crowley v. City and County of San Francisco (1976)
64 Cal.App.3d 450, 458 [rescission of a contract justified by a
material breach by the other party; Taliaferro v. Davis (1963)
216 Cal.App.2d 398, 412 [“where the consideration fails in whole
or in part through the fault of a party whose duty it is to render
it, the other party may invoke such failure as a basis for
rescinding or terminating the contract, provided the failure or
refusal to perform constitutes a breach in such an essential
particular as to justify rescission or termination”].) A material
20
breach by the other party is also a defense to an action for breach
of contract. (Taliaferro, at p. 411.) Accordingly, whether TGS
had the right to rescind depended on whether Pacific breached
the lease by failing to acquire the property within the time the
lease contemplated.
Pacific contends the lease did not require it to purchase the
property before February 28, 2020, and thus it could not have
breached the lease by that date. Pacific makes several
contentions in this regard. First, it urges that pursuant to the
lease’s plain language, its time to obtain title to the property was
governed by the purchase agreement with ExxonMobil. Because
Pacific had until March 31, 2020 to close under the amended
purchase agreement with ExxonMobil, Pacific says it could not
have breached its obligation under the lease to obtain title before
that date. Alternatively, Pacific contends that it was not
required to purchase the property until after TGS submitted its
PPR request, which TGS had not done as of February 28, 2020.
We consider these contentions below.
B. Pacific’s time to acquire the property was not
governed by the terms of the amended
purchase agreement.
Pacific contends that because the lease required it to
acquire the property “pursuant to” the purchase agreement with
ExxonMobil, its deadline to close under the purchase agreement
also governed its time to acquire the property under the lease.
Thus, Pacific says, because it had until March 31, 2020 to
perform under the purchase agreement, it also had until
March 31, 2020 to perform under the lease. For the reasons that
follow, we disagree.
21
A lease is a contract subject to ordinary rules of contract
interpretation. (Castaic Studios, LLC v. Wonderland Studios
LLC (2023) 97 Cal.App.5th 209, 214; Bates v. Industrial Property
Holding Co. (1957) 155 Cal.App.2d 697, 700.) To interpret a
contract, we look to its language and ascertain the intent of the
parties, if possible, based solely on the contract’s written
provisions. (Hewlett-Packard Co. v. Oracle Corp. (2021)
65 Cal.App.5th 506, 531; Civ. Code, §§ 1636, 1637.) “The whole of
a contract is to be taken together, so as to give effect to every
part, if reasonably practicable, each clause helping to interpret
the other.” (Civ. Code, § 1641; see also Arriagarazo v. BMW of
North America, LLC (2021) 64 Cal.App.5th 742, 748 [contract
considered “as a whole”].) On appeal, unless the meaning of the
contract turns on conflicting extrinsic evidence, our review is
de novo. (Hewlett-Packard, at pp. 531–532.)
Pacific contends that section 1.21 of the lease can plausibly
be construed to mean that Pacific’s time to close under the lease
was governed by its time to close under the purchase agreement,
and we agree. Section 1.21 said the lease was “contingent upon
the transfer of fee title to the Land to Landlord pursuant to that
certain Purchase and Sale Agreement to be executed . . . by and
between ExxonMobil . . . and [Pacific].” (Capitalization omitted,
italics added.) As Pacific suggests, this language is reasonably
susceptible of an interpretation that the lease required Pacific to
purchase the property “pursuant to” the purchase agreement—
that is, according to the purchase agreement’s terms.
That is not the end of the inquiry, however. Courts will not
enforce contract terms that give a party complete discretion over
its own performance. Our Supreme Court has explained:
“ ‘[P]romissory words are illusory if they are conditional on some
22
fact or event that is wholly under the promisor’s control and
bringing it about is left wholly to the promisor’s own will and
discretion.’ ” (Asmus v. Pacific Bell (2000) 23 Cal.4th 1, 15; see
also Forecast Homes, Inc. v. Steadfast Ins. Co. (2010)
181 Cal.App.4th 1466, 1483 [same].) Thus, “ ‘[w]hen a party is
given absolute discretion by express contract language, the courts
will imply a covenant of good faith and fair dealing to limit that
discretion in order to create a binding contract and avoid a
finding that the promise is illusory.’ ” (Hester v. Public Storage
(2020) 49 Cal.App.5th 668, 680, fn. 3; see also Storek & Storek,
Inc. v. Citicorp Real Estate, Inc. (2002) 100 Cal.App.4th 44, 57
[same].)
Similarly, Civil Code section 1657 provides that if no time
is specified for the performance of an act required to be performed
under a contract, “a reasonable time is allowed.” (See
The McCaffrey Group, Inc. v. Superior Court (2014)
224 Cal.App.4th 1330, 1351 [quoting statute]; Bushansky v. Soon-
Shiong (2018) 23 Cal.App.5th 1000, 1008 [“ ‘where no time is
fixed for the performance of a condition precedent, it will be
presumed that it is to be performed within a reasonable time’ ”];
Patel v. Liebermensch (2008) 45 Cal.4th 344, 351 [“A legion of
cases supports the proposition that a reasonable time for
payment may be implied in a contract for the sale of real
property”].) This prevents a contracting party from “postpon[ing]
. . . indefinitely” its obligation to perform under a contract.
(Wagner Construction Co. v. Pacific Mechanical Corp. (2007)
41 Cal.4th 19, 29; Woodard v. Glenwood Lumber Co. (1915)
171 Cal. 513, 518–519.)
In the present case, the lease did not specify a date by
which Pacific had to buy the property, and the purchase
23
agreement to which the lease referred had not yet been drafted.
Were we to interpret the lease as Pacific suggests, Pacific could
have extended indefinitely its time to perform its primary
obligation under the lease—to acquire fee title to the property—
thus rendering the lease unenforceable. Instead, having
reviewed the terms of the lease de novo, we agree with the
referee that Civil Code section 1657 and the implied covenant of
good faith and fair dealing required Pacific to complete the
purchase of the property within a reasonable time.
C. Substantial evidence supported the referee’s
conclusion that Pacific did not acquire the
property within a reasonable time.
Having concluded that the lease required Pacific to
purchase the property within a “reasonable” time, we next
consider whether the referee erred by finding that Pacific’s
failure to purchase the property by February 28, 2020 was
unreasonable. For the reasons that follow, we find no error.
“ ‘[W]hat constitutes a reasonable time is a question of fact,
depending upon the situation of the parties, the nature of the
transaction, and the facts of the particular case.’ ” (Wagner
Construction Co. v. Pacific Mechanical Corp., supra, 41 Cal.4th at
p. 30, quoting Sawday v. Vista Irrigation Dist. (1966) 64 Cal.2d
833, 836; see also Kotler v. PacifiCare of California (2005)
126 Cal.App.4th 950, 956.) We review the referee’s finding that
Pacific did not purchase the property within a reasonable time for
substantial evidence. (See Eidsmore v. RBB, Inc. (1994)
25 Cal.App.4th 189, 194–195; Marshall & Co. v. Weisel (1966)
242 Cal.App.2d 191, 195.)
Substantial evidence supported the trial court’s conclusion
that Pacific failed to close on the property within a reasonable
24
time. Section 31.7 of the lease provided that “[t]ime is of the
essence with respect to performance of every provision of this
Lease in which time or performance is a factor.” Delay in
performance is a material failure “ ‘if time is of the essence, i.e., if
prompt performance is, by the express language of the contract or
by its very nature, a vital matter.’ ” (City of Larkspur v. Marin
County Flood Control etc. Dist. (1985) 168 Cal.App.3d 947, 954,
italics omitted; Johnson v. Alexander (1976) 63 Cal.App.3d 806,
813.)
Further, the option agreement that Pacific and ExxonMobil
entered into before the lease was executed provided that Pacific
and ExxonMobil would enter into a purchase agreement by
November 15, 2018. The option agreement provided that the
purchase agreement would include a six-month due diligence
period, which could be extended for up to four months in
exchange for an additional $50,000 payment per 30-day
extension, and a closing date no later than 10 days after the
expiration of the due diligence period. As Paliwal conceded at
trial, the option agreement thus contemplated that Pacific and
ExxonMobil would enter into a purchase agreement no later than
November 15, 2018, and would close no later than ten months
and ten days later, or on or before September 25, 2019.
The testimony at trial suggested that TGS, Jushi, and
ExxonMobil all anticipated, consistent with the option
agreement’s terms, that Pacific would close on the property in
summer or fall 2019. Woloveck said he expected Pacific to close
shortly after TGS was selected in July 2019 to move ahead in the
licensing process, and he told Paliwal sometime between July and
October 2019 that “it’s time to buy the property.” Woloveck
continued to repeat that sentiment to Paliwal “plenty of times”
25
thereafter. Blechner similarly testified that he was “surprised”
and “concerned” that Pacific had not closed by fall 2019, as was
CEO Cacciopo.2 And, ExxonMobil’s Steelman told Paliwal in a
February 2020 letter that the purchase agreement had
specifically anticipated that Pacific would close “in 2019” and his
failure to do so was “unacceptable.”
Further, the evidence did not compel the conclusion that
Pacific’s failure to purchase the property by February 28, 2020
was due to factors beyond its control that might have justified the
delay. To the contrary, Paliwal testified that he intentionally
delayed the purchase “to save on expenses.” Yanko’s testimony
was similar: He said Pacific delayed the purchase consistent
with its “general business practice” of “mitigat[ing] risk as much
as possible and not incur[ring] costs that weren’t 100-percent
certain to bear fruit.” In short, Paliwal and Yanko’s testimony
suggested that their delay was intentional and strategic.
Pacific contends that the referee’s conclusion that its delay
in purchasing the property was unreasonable was inconsistent
with the lease’s “carefully-drawn and time-limited termination
provisions” intended to protect Pacific from “capital risk.” Not so.
2 Pacific suggests that Blechner “impliedly agreed” to extend
the closing date to March 31, 2020 by writing in an internal email
that he was “ ‘relieved that [the] land purchase from ExxonMobil
got extended.’ ” Not so. Blechner testified that his email said
Paliwal was “relieved” that the closing date had been extended,
not that Blechner himself was. But in any case, Blechner’s
internal communications to other Jushi principals could not have
constituted consent to Pacific’s extension request. (See, e.g.,
Cedars-Sinai Medical Center v. Shewry (2006) 137 Cal.App.4th
964, 980 [undisclosed intent is irrelevant to the meaning of a
contract].)
26
The termination provisions Pacific identifies allowed the parties
to terminate the lease if the City failed to issue a cannabis license
or building permits within specified periods of time. In other
words, these provisions recognized that TGS’s and Pacific’s
ability to move forward with the project relied in part on actions
by the City, and it set out conditions under which the parties
could terminate the lease if the City failed to take those actions.
Those provisions are irrelevant to Pacific’s duty to perform its
obligations under the lease that did not depend on the City,
including its obligation to purchase the property. The referee did
not err in so concluding.
D. Pacific’s failure to purchase the property
within a reasonable time was not excused.
Pacific contends that even if it was required under the
lease to acquire the property prior to February 28, 2020, its
failure to do so was excused by TGS’s failure to timely submit its
PPR request. Pacific urges that under the terms of the lease, it
was not required to close on the property until after TGS
obtained a cannabis permit. Because TGS did not have a
cannabis permit on February 28, 2020—and, indeed, had not yet
submitted the PPR request—Pacific contends the referee erred by
finding that its failure to close breached the lease.
We do not agree. Paliwal conceded at trial that nothing in
the lease’s plain language required TGS to acquire a cannabis
permit before Pacific obtained title to the property:
“Q: [Y]ou . . . understand that there was nothing in the
lease that made your obligation to purchase the property
contingent on Jushi or TGS obtaining [a cannabis] license; right?
“A: That is correct.”
27
“Q: And there’s nothing in the lease that permits Pacific
Collective to delay their obligation to purchase the property;
correct? [¶] . . . [¶]
“A: Correct.”
“Q: And there’s nothing in the lease that says that . . .
Pacific Collective’s obligation to purchase the property is
contingent on anything; is that right? [¶] . . . [¶]
“[A]: That is correct.”
Paliwal’s concession was consistent with the lease’s plain
language. As discussed, section 1.21 provided that the lease was
contingent on the transfer of title to the property to Pacific.
Separately, section 1.18 required TGS to apply for a cannabis
license “promptly” and “diligently.” Section 1.21 did not say that
Pacific’s obligation to obtain title was conditioned on TGS’s
obtaining a cannabis license—and, indeed, while section 1.18
expressly allowed TGS to terminate the lease if it did not obtain a
cannabis license, section 1.18 did not permit Pacific to do so.
The absence of an express condition in section 1.21 is
particularly notable in light of section 1.15, which said that
Pacific was not obligated to “construct the Improvements” until
TGS obtained all applicable permits to operate a retail cannabis
business from the property. Had Pacific’s obligation to purchase
the property likewise been contingent on TGS obtaining
applicable permits, the parties presumably would have said so.
They did not.
Pacific also contends that TGS’s obligation to obtain a
cannabis permit necessarily preceded Pacific’s obligation to
purchase the property because “[w]hile Pacific’s purchase was ‘to
be executed’ in the future, the Lease nevertheless provided that
[TGS’s] duties were immediate.” But as we have said, the lease’s
28
plain language did not condition Pacific’s obligation to purchase
the property on TGS’s obtaining a permit. Instead, the lease
described Pacific’s obligation to purchase the property and TGS’s
obligation to seek a cannabis permit as independent obligations
to be performed simultaneously. We will not read into the lease a
term the parties did not include. (Dameron Hospital Assn. v.
AAA Northern California, Nevada & Utah Ins. Exchange (2014)
229 Cal.App.4th 549, 569 [“ ‘Courts will not add a term about
which a contract is silent’ ”]; Vons Companies, Inc. v. United
States Fire Ins. Co. (2000) 78 Cal.App.4th 52, 59 [“We do not have
the power to create for the parties a contract that they did not
make and cannot insert language that one party now wishes were
there”].)
Pacific further contends that interpreting the lease to
require it to purchase the property before TGS obtained a
cannabis permit is “harsh” and “inequitable” because it would
compel Pacific to “risk laying out almost $6 million dollars only to
discover that TGS could not—or would not—obtain a Culver City
cannabis license.” Perhaps so, but that is the deal Pacific struck.
Finally, Pacific contends that Pacific’s purchase of the
property was not a condition precedent to TGS’s obligation to
submit the PPR request. We need not reach this issue. As the
plaintiff, Pacific had to prove not only that TGS breached the
lease, but also that Pacific performed or was excused from
performing. (Oasis West Realty, LLC v. Goldman, supra,
51 Cal.4th at p. 821; Coyote Aviation Corp. v. City of Redlands,
supra, 111 Cal.App.5th at p. 973.) Because the record supports
the referee’s findings that Pacific neither performed nor was
excused from performing, an affirmance would be warranted even
if TGS or Jushi breached the lease. (See Phillips v. Volvo Penta
29
of the Americas, LLC (2026) 120 Cal.App.5th 1173, 1189 [because
plaintiff has the burden to prove all elements of claim, failure to
establish any element “is fatal to his case”].)
For all the foregoing reasons, we conclude that the lease
required Pacific to purchase the property within a reasonable
time, and substantial evidence supported the referee’s findings
that Pacific’s delay was unreasonable and was not excused by
TGS’s failure to submit its PPR application. We therefore affirm
the judgment for defendants.
30
DISPOSITION
The judgment is affirmed. TGS and Jushi are awarded
their appellate costs.
NOT TO BE PUBLISHED IN THE OFFICIAL
REPORTS
ASHWORTH, J.*
We concur:
ADAMS, P. J.
HANASONO, J.